Super Sweet’s Amino Acid Expansion Project

Yuwang Bio Completed Crystal Glucose Project

Recently, the completion environmental-protection acceptance report for the first-phase of starch deep-processing project—150,000 t/a of crystalline glucose—of Inner Mongolia Yuwang Biological Technology Co., Ltd. (Yuwang Bio) was published on an environmental platform.

 

Project overview

  • Nature: Expansion & retrofit
  • Location: Holingol City, Tongliao City, Inner Mongolia Autonomous Region
  • Total investment: RMB 517 million
  • Product plan: 150,000 t/a of crystalline glucose
  • Main feedstock: 356,132 t/a of starch slurry (in-house)
  • Labor quota: 80 new employees
  • Working system: three 8hr shifts per day, 300 working days per year
  • Progress:
    • Approval of EI report: Feb. 2025
    • Started construction: March 2025
    • Completion: Jul. 2025
    • On-site acceptance monitoring: 21–22 Jul., 2025

You can get more information on China’s corn deep-processing industry by checking out NK Corn Deep-Processing China News. Follow our LinkedIn to get more industry news.

Weifang Jianbao Completed Corn Protein Project

Weifang Jianbao Completed Corn Protein Project

Weifang Jianbao Biotechnology Co., Ltd. (Weifang Jianbao) previously outsourced starch slurry to produce 105,000 t/a of glucose (dried) and subsequently 100,000 t/a of sodium gluconate.

Recently, the company completed its “38,000 t/a of corn protein project”. Thus, Weifang Jianbao has expanded the entire industrial chain, purchasing corn to produce starch slurry (No more outsourcing), and then glucose and sodium gluconate.

Project overview

  • Nature: New construction
  • Location: Zhuliu Chemical Industry Park, Changle County, Weifang City, Shandong Province
  • Total Investment: USD50.07 million (RMB360 million), of which USD2.5 million (RMB18 million) is for environmental protection.
  • Key raw materials: 508,000 t/a of corn
  • Labor quota: 68 workers
  • Working system: Three-8hr-shift per day, 300 working days totaling 7,200 hours per year
  • Progress:
    • Approval of EI report: Apr. 2023
    • Starting construction: Jun. 2023
    • Completion: Aug. 2024
    • On-site environmental monitoring: 16-25 Aug., 2024
  • Product plan of this project
Product Capacity (dry weight), t/a Capacity (wet weight), t/a Moisture content of wet products
Corn protein 38,000 41,800 9%
Starch slurry 301,000 720,700 58.24%
Fiber feed 67,700 73,600 8.01%
Corn germ 31,600 34,300 7.86%

 

Check out NK Corn Deep-Processing China News or email us at contact@nkmarketresearch.com.