Jiaozuo Huakang’s Xylose Energy-saving Reconstruction Project

Norchem Biotech’s Inositol and Liquid Sugar Project

On 7 March, the local ecological environment bureau accepted and publicized the environmental impact report for the inositol and liquid sugar mixture project of Hunan Norchem Biotech Co., Ltd. (Norchem Biotech).

Project overview

  • Nature: Expansion and renovation
  • Location: Jinshi High-tech Industrial Development Zone, Hunan Province
  • Total investment: USD1.4 million (RMB 10 million)
  • Product plan: 1,000 t/a of inositol (feed grade) 30,000 t/a of 58.5% liquid sugar mixture (composition: sucrose 60%, fructose 20%, glucose 20%)
  • Process flow:
    • Utilizing enzymes produced by microbial fermentation to hydrolyze starch, followed by purification and refining processes to produce inositol.
    • Sugar juice (with 15% sugar content) undergoes a series of refining and purification processes, including high-temperature sterilization, adsorption decolorization, plate and frame filtration, and concentration, to obtain the liquid sugar mixture.
  • Labor quota: 30 new employees
  • Working system: Three 8hr shifts per day, 300 working days per year.
  • Construction period: 6 months

 

Currently, Norchem Biotech can produce 10,000 t/a of saccharification enzyme, 300 t/a of adenosine, 2,000 t/a of feed-grade calcium pantothenate, 2,000 t/a of food-grade alanine, and 1,500 t/a of cytidine.

 

You can get more information on China’s corn deep-processing industry by checking out NK Corn Deep-Processing China News.

Haotian Pharm Completed Gluconolactone and Inositol Project

Haotian Pharm Completed Gluconolactone and Inositol Project

According to the monitoring report publicized recently, Zhucheng Haotian Pharm Co., Ltd. (Haotian Pharma) completed its gluconolactone and inositol project.

Project overview

  • Nature: Expansion
  • Address: Xinxing Town, Zhucheng City, Weifang City, Shandong Province
  • Total Investment: USD13.9 million (RMB100 million), of which USD0.2 million (RMB 1.5 million) is for environmental protection
  • Product plan: 2,000 t/a of gluconolactone and 5,000 t/a of inositol
  • Main raw materials: 1,926 t/a of glucose, 5,000 t/a of inositol crude (purchased), etc.
  • Labor quota: 160 employees.
  • Working system: Three-8hr-shift per day, 300 working days totaling 7,200 hours per year.
  • Process:
    • Approval of EI report: 12 Sept., 2024
    • Starting construction: 20 Sept., 2024
    • Completion: 25 Oct., 2024
    • On-site environmental monitoring: 24 Nov. to 25 Nov., 2024.

You can get more information on China’s corn deep-processing industry by checking out NK Corn Deep-Processing China News or email us at contact@nkmarketresearch.com.