Heilongjiang Yuchuang Completed Furfuryl Alcohol Project (Phase I)

Heilongjiang Yuchuang Completed Furfuryl Alcohol Project (Phase I)

According to the completion environmental-protection acceptance monitoring report published on an environmental platform recently, Heilongjiang Yuchuang Biomass Material Co., Ltd. (Heilongjiang Yuchuang) has completed Phase I of the furfuryl alcohol project.

 

Project overview

  • Nature: New construction
  • Location: Linyuan Chemical Park, Daqing Hi-Tech Zone, Heilongjiang Province
  • Total investment: RMB 170 million, of which RMB 8.88 million is for environmental protection
  • Construction content: furfural production line and supporting facilities
  • Product plan: 10,000 of t/a furfural
  • Main raw material: 150,000 t/a corncobs
  • Manning: existing 46 personnel
  • Work pattern: 330 production days per year, 4-shift/3-rotation system, 8 hours per shift
  • Progress:
    • Approval of EI report: Apr. 2024
    • Started construction: May 2024
    • Completion: Jun. 2025
    • On-site acceptance monitoring: 22–30 Oct., 2025

 

Phase II, which would add 10,000 t/a of furfural, 50,000 t/a of furfuryl alcohol and 6,000 t/a of 2-methylfuran production lines together with their supporting facilities, has not yet started construction.

 

You can get more information on China’s corn deep-processing industry by checking out NK Corn Deep-Processing China News. Follow our LinkedIn to get more industry news.

Posted in Corn deep-processing, Food ingredient and Feed additive and tagged .

Leave a Reply

Your email address will not be published. Required fields are marked *